Sprint Brief is an Agent Skill for productivity published in the majiayu000/claude-skill-registry repository on GitHub: a SKILL.md instruction file an AI agent can load to do this task.

Generate a structured sprint brief from sprint data and goals. Use when asked to write a sprint brief, create a sprint summary, document sprint goals and scope, or produce a team-facing sprint overview. Produces a scannable brief with sprint goal, rationale, grouped work, critical path, risks, and definition of done.

View on GitHub ↗
QUICK START

How to use this skill

Bring this guide into your coding agent with a prompt tailored to the tool you use.

  1. Open your project in Codex.
  2. Copy and paste the prompt below.
  3. Review files and risks before approving any action.
Prompt to paste
Inspect the Agent Skill at https://github.com/majiayu000/claude-skill-registry/blob/HEAD/skills/development/unknown-mohitagw15856-pm-claude-skills-10/SKILL.md and all supporting files. Report provenance, permissions, scripts, dependencies, and security risks. Propose an exact installation into .agents/skills/sprint-brief, but wait for my approval before writing files or running scripts.

Copying this prompt does not install or run the skill. Review third-party files before use.

Sprint Brief Skill

Produce a clear, scannable sprint brief that every team member — engineer, designer, PM — can read in under three minutes and understand exactly what we're doing and why.

Required Inputs

Ask the user for these if not provided:

  • Sprint name and number
  • Sprint goal (1-2 sentences — flag if too vague)
  • Ticket list with owners (or a description of the work)
  • Known dependencies or blockers
  • Carry-over items from previous sprint (if any)

Process

  1. Read sprint goal and check it's specific and measurable — flag if it's too vague
  2. Group tickets by theme or feature area
  3. Identify the critical path — which tickets must complete for the sprint goal to be met?
  4. Flag risks: tickets with unclear acceptance criteria, missing designs, unresolved dependencies
  5. Note carry-over items and whether they affect this sprint's goal
  6. Validate — Confirm the sprint goal is achievable given the ticket scope and capacity. If the critical path items alone would fill the sprint, flag it as overloaded.

Output Structure

Sprint [Number] Brief — [Dates]

Sprint Goal: [1-2 sentences — specific and measurable] Why This Sprint Matters: [Connect to quarterly OKR in 2-3 sentences]

What We're Building:

  • [Theme 1]: [tickets and owners]
  • [Theme 2]: [tickets and owners]

Critical Path: [The 2-3 tickets everything else depends on]

Risks to Flag:

  • [Risk 1 + mitigation]
  • [Risk 2 + mitigation]

Carry-over from Last Sprint: [List + impact on current goal]

Definition of Done: [Specific, agreed criteria for sprint success]

Quality Checks

  • Sprint goal is specific enough to score pass/fail at the end of the sprint
  • Critical path items are named — not just "the important ones"
  • Every risk has a mitigation or owner (not just "this is a risk")
  • Carry-over items are connected to their impact on this sprint's goal
  • Definition of Done is agreed criteria, not a task list